Creating a Break Point

Use

You can use this procedure to create a cost structure that deviates from the production structure.

Prerequisites

  • You have entered a distribution profile in the project definition.

  • You have assigned the individual work breakdown structure (WBS) elements of your project to one or more grouping WBS elements.

Procedure

  1. In Command , enter PEG03 .

    The Change View "Breakpoint Maintenance": Overview screen appears.

  2. Choose New entries .

  3. Enter the required data.

    You must name a WBS element or a network activity as the break point.

  4. Choose Save .

Result

You can use the break point you have created as a cost assignment element. The costs of a replenishment element are now assigned to the break point instead of to the WBS element that created the requirement.